This document constitutes the Environmental and Social Impact Assessment (ESIA) of the Installation of 3.1 Rooftop Solar PV System at RIL and has been developed by a multi-disciplinary team in close collaboration with the management of Rising Industry Ltd. The report is prepared following the ESIA guidelines for Industries (DoE, ECR 2023, to a certain extent, but not limited to those.
All the relevant social and environmental risks and potential impacts have been taken due care of as part of the assessment in compliance with the Performance standards set by the World Bank (WB), KfW, and JICA besides following the guidelines set forth by DoE.
The ESIA presents background information about the project. Several national legislations which the project should abide by have been presented. A baseline environmental examination was conducted by the consultants. The project activities were closely examined to find the relationship and dependency between project activities and environmental components. This information was used to identify the impacts of the project activities on the surrounding environment. Later on, the evolution of this impact was done by examining existing environmental components. Several mitigation measures to reduce adverse impacts were suggested. Finally, a management plan with monitoring requirements was developed.
This document constitutes the Environmental Impact Assessment (ESIA) of the Installation of 3.3 MWp as the first phase of 30 MW Grid-Connected Rooftop Solar PV System at Walton Hi-Tech Industries PLC and has been developed by a multi-disciplinary team in close collaboration with the management of Walton Hi-Tech Industries PLC.
All the relevant social and environmental risks and potential impacts have been taken due care of as part of the assessment in compliance with the Performance standards set by the World Bank (WB), KfW, and JICA besides following the guidelines set forth by DoE.
The ESIA presents background information about the project. Several national legislations which the project should abide by have been presented. A baseline environmental examination was conducted by the consultants. The project activities were closely examined to find the relationship and dependency between project activities and environmental components. This information was used to identify the impacts of the project activities on the surrounding environment. Later on, the evolution of this impact was done by examining existing environmental components. Several mitigation measures to reduce adverse impacts were suggested. Finally, a management plan with monitoring requirements was developed.
This document constitutes the Environmental and Social Impact Assessment (ESIA) of the Installation of 327 kWp Rooftop Solar PV System at Saiham Knit Composite Ltd. and has been developed by a multi-disciplinary team in close collaboration with the management of Saiham Knit Composite Ltd. The report is prepared following the ESIA guidelines for Industries (DoE, ECR 2023, to a certain extent, but not limited to those.
All the relevant social and environmental risks and potential impacts have been taken due care of as part of the assessment in compliance with the Performance standards set by the World Bank (WB), KfW, and JICA besides following the guidelines set forth by DoE.
The ESIA presents background information about the project. Several national legislations which the project should abide by have been presented. A baseline environmental examination was conducted by the consultants. The project activities were closely examined to find the relationship and dependency between project activities and environmental components. This information was used to identify the impacts of the project activities on the surrounding environment. Later, the evolution of this impact was done by examining existing environmental components. Several mitigation measures to reduce adverse impacts were suggested. Finally, a management plan with monitoring requirements was developed.
NAAFCO Pharma Limited, one of Bangladesh's major integrated medicine manufacturing companies, proposed a project of 1.494 MWp rooftop solar PV systems on the roofs of different sheds and buildings of NAAFCO Pharma Limited.
Basically, this part provides the Project background, the aim and scope of the study, and the approach and methodology of the proposed project.
This paper contains the findings of an Environmental and Social Impact Assessment (ESIA) of the project titled "1.494 MWp Industrial Rooftop Solar Project of NAAFCO Pharma Limited, Bhaluka, Mymensingh." The main purpose of the ESIA study is to identify, evaluate and manage environmental and social impacts that may arise due to implementation and operation of the project. The site visit for the ESIA study has been undertaken to assess any potential impacts (both negative and positive) that may arise from the construction, operation and decommissioning of the rooftop solar plant. The goal of the ESIA is to enhance the sustainability of vital ecosystems, to improve or restore ecosystem health and biodiversity. The document has been made to comply with the requirements of World Bank Group's EHS Guidelines and applicable sector guidelines, as well as applicable local and national regulations.
This study relied on both primary and secondary data and information. The primary data includes data collected from field observations and secondary data includes a review of the statistical and relevant information from Government Departments. Discussions were held with stakeholders including community representatives and a wide range of project areas.
Hatil Complex Ltd. has planned to install a 2.669 MWp Solar On-Grid power system on the roof-top of their existing plant of Unit-01 and Unit-02. The proposed solar project will be able to generate a good amount of electricity for HCL situated at Domna, Muslimtek, Kashimpur, Gazipur-1700, Bangladesh.
In the proposed system, two leading pieces of equipment will be used: solar panels and inverters. Sun shines on the solar panels to generate DC electricity. The inverters will convert the DC electricity from the solar panel to 440V 3-phase AC. Then, the energy will be fed into the bus bars of industry.
The study’s objective is to examine and assess the project's environmental and social impacts. An environmental management and monitoring plan have also been developed with an indication of the extent of work to be done to minimize the impacts.
Rancon Motorbikes Ltd. (RMBL) has planned to install 350.46 KWp Solar On-Grid power system at on the roof-top of their existing plant. The proposed solar project will be able to generate a good amount of electricity for RMBL situated at 133/2 Boro Bhobanipur, Kashimpur, Gazipur, Bangladesh.
In the proposed system two main pieces of equipment will be used which are panels and inverters. Sun shines on the solar panels to generate DC electricity. The DC electricity produced from the solar panel will be converted to 440V 3-phase AC using the inverters. Then, the energy will be fed into the bus bars of industry. A Zero Export Controller will be used to ensure ‘Net Zero Export’.
The objective of the study is to provide an examination and assessment of the environmental and social impacts of the project. An environmental management and monitoring plan has also been developed with an indication of the extent of work to be done to minimize the impacts.
The project involves construction and operation of a biogas-based power plant at Satghoria, Halodia, Laohajung, Munshiganj by Dutch Dairy Limited (DDL). The GPS location of the project site is 23.47803˚N, 90.29655˚E. The project is located within the premise of the dairy farm of DDL.
The main objective of this project is to use 34 tons of dung produced everyday by Farm Cattle, Sheep and Goats to generate electricity via Biogas route for captive consumption and raw (unprocessed) organic fertilizer.
The main objective of the Environmental and Social Impact Assessment (ESIA) study is to assess both positive and negative environmental and social impacts due to the project activities; assess the impacts and recommend appropriate mitigation measures during preconstruction, construction, and operation phases to minimize negative impacts of the project to acceptable levels.
These documents constitute the Environmental and Social Impact Assessment (ESIA) of Sirajganj Economic Zone Limited (SEZL), the largest private economic zone in Bangladesh. The project comprises of development of the economic zone measuring total 1041.43 acres out of which current ESIA study will be limited in Phase-1 (415 acres) area only. SEZL at present will develop the off-site and on-site infrastructure to make site accessible and buildable. Facilities include site filling, boundary wall, construction of internal road connectivity with the access road, administration building, internal drainage line, transmission line running across the site. Development of EZ & off-site facilities attracts the applicability of Environment Conservation Act (ECA), 1995 & Environmental Conservation Rules, 1997. The industries planned to be set up are light engineering, textile/ RMG, food processing, leather & leather products, pharmaceuticals, non-metallic minerals and other Industries.
Fakhruddin Textile Mills Ltd. proposed a 2.517 MWp rooftop solar project on their rooftop. The project site is located at Gargaria, Master Bari under Sreepur Upazila within the Gazipur district under Dhaka Division. Sreepur is located in between 24°11'56" North Latitudes and 90°28'41.5" East Longitudes.
In the proposed system two main pieces of equipment will be used which are panels and inverters. Sun shines on the solar panels to generate DC electricity. The DC electricity produced from the solar panel will be converted to 440V 3-phase AC using the inverters. Then, the energy will be fed into the bus bars of industry. A Zero Export Controller will be used to ensure ‘Net Zero Export’.
This document is the Environmental and Social Impact Assessment (ESIA) assessment for a rooftop solar project on Fakhruddin Textile Mills Ltd.’s rooftop. The project proponent will create an Environmental and Social Management Plan (ESMP) as a part of the ESIA. The mitigation measures suggested, environmental and social monitoring and reporting requirements, emergency response procedures, related institutional or organizational arrangements, capacity development and training measures, implementation schedule, and performance indicators will all be included in the ESMP. Where impacts and risks cannot be avoided or minimized, mitigating measures and activities will be established in order for the project to be planned, constructed, and operated in accordance with applicable laws and regulations and to meet the requirements set forth in this document
Khantex Fashions Ltd. proposed a 369.0 kWp rooftop solar project on their rooftop. The project is located at Barotopa, Mawna, Sreepur, Gazipur (24.208688 N, 90.373954 E).
In the proposed system two main equipment will be used which are solar panels and inverters. Sun shines on the solar panels to generate DC electricity. The DC electricity produced from the solar panel will be converted to 440V 3-phase AC using the inverters. Then, the energy will be fed into the bus bars of industry.
This document is the detailed Environmental and Social Assessment (ESA) study for the rooftop solar project on the rooftop of Khantex Fashions Ltd. As part of the ESA, the project proponent will prepare an Environmental and Social Management Plan (ESMP) that addresses the potential impacts and risks identified by the environmental and social assessment. The ESMP will include the proposed mitigation measures, environmental and social monitoring and reporting requirements, emergency response procedures, related institutional or organizational arrangements, capacity development and training measures, implementation schedule, and performance indicators. Where impacts and risks cannot be avoided or prevented, mitigation measures and actions will be identified so that the project is designed, constructed, and operated in compliance with applicable laws and regulations and meets the requirements specified in this document.
"Environmental and Social Management System (ESMS)" guideline for Solar Rooftop & Grid Tied Solar Power projects.
Summit Barisal Power Limited (SBPL) has been awarded to design, engineer, manufacture, finance, construct, complete, permit, test, commission, insure, own, operate and maintain a 110 MW Power Plant to generate and supply electricity to Bangladesh Power Development Board (BPDB) for a period of 15 years as an Independent Power Plant (IPP). Considering the importance of the project to meet the power demand, Infrastructure Development Company Limited (IDCOL) along with some other multilateral financial institutions is considering to finance the project.
According to the Environment Conservation Rules, 1997 of Bangladesh Government, industrial projects in Bangladesh have been categorized into four classes—Green, Amber A, Amber B and Red. Considering the magnitude of generating pollution, power plant project has been classified as Red Category project. So, SBPL project has fallen into Red category. According to the Safeguard Policy statement, 2009 of Asian Development Bank (ADB), power plant project of about 110 MW capacity falls into category B due to the localized impact. As a part of environmental compliance, there is a requirement for preparation of an Environmental Impact Assessment (EIA) according to ECR, 1997 of Department of Environment (DOE) and Initial Environmental Examination (IEE) report according to SPS, 2009 of ADB. The content of IEE of ADB is almost similar to EIA of DOE, except the public consultation aspects as is required by ADB. SBPL has already engaged Bangladesh Centre for Advanced Studies (BCAS) to prepare the IEE according to the requirement of ADB as well as the DOE.
NOx, SOx, noise and lube oil are the main issues to consider from environmental pollution perspective of the said power plants. As a guiding standard, SBPL has to comply with the national standards of Bangladesh. Where national standards are not available, SBPL has to comply with the best practices like ‘Environmental, Health and Safety Guidelines of IFC’.
IDCOL is careful about maintaining environmental and social safeguards. It encourages all, having any complain or observation regarding any matter of the Projects, to contact IDCOL management.
For the Environmental Impact Assessment Report please click on the link below:
Summit Narayangonj Power Unit-II Limited (SNPU2L) has been awarded to design, engineer, manufacture, finance, construct, complete, permit, test, commission, insure, own, operate and maintain a 55 MW Power Plant to generate and supply electricity to Bangladesh Power Development Board (BPDB) for a period of 15 years as an Independent Power Plant (IPP). Considering the importance of the project to meet the power demand, Infrastructure Development Company Limited (IDCOL) along with some other multilateral financial institutions is considering to finance the project.
According to the Environment Conservation Rules, 1997 of Bangladesh Government, industrial projects in Bangladesh have been categorized into four classes—Green, Amber A, Amber B and Red. Considering the magnitude of generating pollution, power plant project has been classified as Red Category project. So, SNPU2L project has fallen into Red category. According to the Safeguard Policy statement, 2009 of Asian Development Bank (ADB), power plant project of about 110 MW capacity falls into category B due to the localized impact. As a part of environmental compliance, there is a requirement for preparation of an Environmental Impact Assessment (EIA) according to ECR, 1997 of Department of Environment (DOE) and Initial Environmental Examination (IEE) report according to SPS, 2009 of ADB. The content of IEE of ADB is almost similar to EIA of DOE, except the public consultation aspects as is required by ADB. SNPU2L has already engaged Bangladesh Centre for Advanced Studies (BCAS) to prepare the IEE according to the requirement of ADB as well as the DOE.
NOx, SOx, noise and lube oil are the main issues to consider from environmental pollution perspective of the said power plants. As a guiding standard, SNPU2L has to comply with the national standards of Bangladesh. Where national standards are not available, SNPU2L has to comply with the best practices like ‘Environmental, Health and Safety Guidelines of IFC’.
IDCOL is careful about maintaining environmental and social safeguards. It encourages all, having any complain or observation regarding any matter of the Projects, to contact IDCOL management.
For the Environmental Impact Assessment Report please click on the link below: